Extending life of nuclear plants helps ease energy demand pressure
Photo Robinson NPP, South Carolina (Photo credit: Duke Energy)
Life extension of existing nuclear power plants is rapidly emerging as an viable option for countries facing an energy deficit in the coming decades. With electricity demand accelerating, the global reactor fleet is hitting an “unyielding demographic wall” of age: the IAEA notes that nearly 67% of the world's nuclear capacity is more than 30 years old, and 41% has operated for more than 40 years – the original design life for most of these facilities.
The US Department of Energy (DoE) says the industry has recognised since the mid-1970s that major portions of NPPs could last much longer than the duration of the original licences, was normally was 40 years. Recent studies have concluded that refurbishing plants – even at substantial cost – would be economically beneficial to their stakeholders. It would also draw on the skills of the broad nuclear industry supply chain – the ecosystem represented across the board at WNE – at every step of the process from approval to completion.
The world as a whole is belatedly waking up to the importance of nuclear power in the overall energy mix. After more than two decades of stagnation, the capacity of the global nuclear fleet is expected to increase by one-third by 2035.
That’s the projection of the latest World Energy Outlook from the International Energy Agency (IEA) based on existing energy policies and the expectation of “a record high in nuclear power output” in 2025.
"Technology advances… are improving the outlook for nuclear power,” says the report. “As demand surges and the need for reliable, low-emission baseload electricity increases, nuclear is increasingly seen as a critical part of a secure, affordable and diverse electricity mix."
It’s a welcome reversal in fortune for the nuclear industry, which had “suffered some decline and stagnation” from the late 1970s to early 2000s, although its share of world electricity generation remained at 16-17 per cent.
Now, with the very public support for nuclear by the current US administration, the French government’s new multiyear energy programme (PPE) putting renewed focus on nuclear, and other countries looking into it, the nuclear industry appears to be gaining momentum. This point was not lost on the international visitors, delegates and exhibitors who attended the 2025 edition of the World Nuclear Exhibition (WNE) in record numbers and contributed to the buzz in the exhibition hall and conference rooms.
WNE 2023_© Collectif Favart
Approval varies country to country, and usually follows a pattern, starting with a comprehensive assessment of how ageing has affected structures, systems and components. Every part of the plant is checked for its compliance with current standards, not those which applied when it was built, and the operator puts forward a plan to close any gaps with upgrades or retrofits. Public consultations and inspections at this stage will be taken into account by the regulator in deciding to grant a licence renewal with or without conditions.
Operation to the age of 80 years
In the US, where expanding the domestic nuclear capacity is a priority of the current administration, life extension programmes have taken off. Numerous sites have been granted renewals of 20 years that allow operation to 80 years. One of the most recent, Robinson NPP in South Carolina, benefited from the US government’s push to streamline the process when it received the green light for its renewal in just 12 months. In total, the Nuclear Regulatory Commission (NRC) approved life extensions to 13 reactors in 2025.
The US is also bringing back to life three closed plants in what’s being described as an “unprecedented move” driven by rising demand, including from data centres. The Department of Energy (DoE) has earmarked up to $4.4 billion in loans to restore a total of 2.25 GW across the three sites: Palisades in Michigan, which shut down for decommissioning in 2022; Crane in Pennsylvania, shut down in 2019; and Duane Arnold in Iowa, closed in 2020. Microsoft and Google are involved in Crane and Duane Arnold respectively as part of their strategy to secure large amounts of clean energy for their data centres.
Photo Crane Clean Energy Center, Pennsylvania (Photo credit: Constellation Energy)
Decommissioning plans abandoned
Across Europe, several countries are actively studying – and running – life extension programmes. Some have reconsidered earlier decisions on shutdowns.
France published its third 10-year energy policy (PPE3) earlier this year and in it officially abandoned decommissioning plans in favour of extending the lifespan of existing reactors after the regulator found no technical obstacles that EDF could not address through studies, operational adjustments, or equipment upgrades. “The strongest near-term capacity route [for France] is long-term operation of the existing fleet,” commented the World Nuclear Association (WNA).
Elsewhere, in the Czech Republic, work started last spring on extending the working life of four reactors at Dukovany to 80 years, and a similar extension has been announced for the Temelin plant.
Photo Dukovany NPP, Czech Republic (Photo credit: CEZ Group)
IAEA interest in extended life licensing
The IAEA has taken a strong interest in extended life licensing. Its 2026 Nuclear Technology Review highlights the growing importance of maintenance, refurbishment and life extension, giving decision-makers a delicate balancing act between newbuild and extended life capacity.
Since 2007, the IAEA has offered its member states a peer review, or mission, into safety aspects of long-term operation (SALTO). It’s described as “a comprehensive review directly addressing strategy and key elements” for the safe long-term operation of water-modulated reactors. The IAEA says the most suitable time for this review would be in the last 10 years of the plant’s design life. By June 2025, the IAEA had conducted 62 missions at 24 NPPs in 20 member states. Typically, the missions take nine days.
“A number of factors need to be considered to decide on the long-term operation of these installations,” the agency says. “While many of these decisions concern economic viability, all are grounded in the premise of maintaining plant safety.” The evaluation of programmes and performance is made on the basis of the IAEA’s safety standards and other guidance.
At the WNE 2023 conference, Emilie Sauchay, HR Manager of Ineo Nucléaire, discussed their strategic workforce planning for 2022 and 2023. She noted the recruitment of skilled workers as a significant factor but emphasised the necessity of making training programs available for professionals outside of the industry.
“For me, the most important one is to be able to train people in our professions, to be able to attract employees who are not currently in the sector but who would like to join this dynamic sector,” Emilie Sauchay stated. She also added that to support the growth of their workforce, Ineo Nucléaire developed training academies and a network of training centres.
Economic engines for domestic supply chain
Canada’s nuclear fleet, which is concentrated in the province of Ontario and includes what’s described as the world’s biggest operating nuclear facility at Bruce Nuclear, is undergoing significant renewal to extend the life of the CANDU reactors at its Darlington, Bruce, and Pickering sites by 30 years, to well into the second half of this century. The works in total are described as “massive economic engines” for the domestic economy through the tens of thousands of skilled jobs they create directly and indirectly through the supply chain.
Life extension also helps build mainstream capabilities that stretch far beyond the immediate project. In the experience of Ontario Power Generation (OPG) and the work it carried out at Darlington NPP, life extension projects allowed the utility to build capacity in areas including supply chain and skilled workforce. Speaking at WNE 2025, Sandra Dykxhoon, OPG vice-president for New Nuclear Growth, said despite there being no civil engineering works in the Darlington refurbishment, “we did have to pull up the guts of the reactor and rebuild it. It’s still very complex.”
Photo Darlington Nuclear Generating Station, Ontario (Photo credit: OPG)
OPG hopes to take that capability and knowhow forward for both its SMR projects and large nuclear newbuilds planned in the 2030s, lowering the risk on subsequent projects. She said: “We call it ‘walk before we run’.”
Lessons learned in Canada could be applied in other jurisdictions, she added, including some where current debate pitches the concept of SMRs against large reactors (“We like both,” said Dykxhoon) as countries grapple with their future energy needs.
This is a debate that is growing in importance and urgency, and without doubt will be on the agenda at WNE 2027, which runs from 7–9 December 2027 at the Parc des Exposition in Paris Villepinte. Exhibitor registration is now open.